Chat with us, powered by LiveChat Write the project scope statement and work breakdown statement (WBS) for the WAG expansion project. Remember the components that you created WBS.xlsx - Writingforyou

Write the project scope statement and work breakdown statement (WBS) for the WAG expansion project. Remember the components that you created WBS.xlsx

write the project scope statement and work breakdown statement (WBS) for the WAG expansion project. Remember the components that you created 

RACI Example

Step Project Initiation Project Sponsor Project Manager Stakeholder 1 Stakeholder 2 Accounting/Finance
1 Task 1 C A/R I C I
2 Task 2 A I C R I
3 Task 3 A I C R I
4 Task 4 C A/R R I I
Legend:
R Responsible
A Accountable
C Consulted
I Informed

RACI Template

Step Project Initiation Project Sponsor Project Manager Stakeholder 1 Stakeholder 2 Accounting/Finance
1
2
3
4

WBS

Task Sub Task Duration Cost
Equipment move
Labor 4 weeks $5,000
XXXX 2 weeks $1,000
Truck rental 2 weeks $2,500
XXXX 3 weeks $1,500
Equipment Move total 4 weeks total $10,000
Equipment Setup
Labor 4 weeks $7,500
XXXX 2 weeks $1,000
Shipping cost 2 weeks $1,500
XXXX 3 weeks $1,500
Equipment Setup total 4 weeks total $11,500